Review of Problem Tooling Breakdown Fixes at the Op10 Part Panel Anniversary, RR W/House Inn, RR L/R (RH) at Pt. Summit Adyawinsa Indonesia

Authors

  • Elika Tiara Wijaya Universitas Singaperbangsa Karawang Author
  • Dene Herwanto Universitas Singaperbangsa Karawang Author
  • Naufal Rabbani Sumitra Universitas Singaperbangsa Karawang Author

Keywords:

Dies Stamping, Tooling Breakdown, Preventive Maintenance, Fishbone Diagram, 5Why Analysis

Abstract

Anniversary damage in the stamping process is a critical problem that can affect product quality and hinder smooth production in the automotive industry. This study aims to identify the main cause of damage to the OP10 Anniversary of the RR W/House Inn RR L/R (RH) at PT. Adyawinsa Indonesia Summit and formulate the right improvement steps to reduce the frequency of breakdowns. The research uses a case study approach through direct observation, structured interviews with Maintenance Tooling personnel, as well as analysis of OEE data and damage history for the period June–December 2024. The data were analyzed using the Root Cause Analysis method (Fishbone Diagram and 5 Why) as well as technical evaluation on the insert dies component. The results showed that scratch defects  in parts were caused by damage to the blank holder insert in the form of pin holes and peeling hardchrome layers, which was exacerbated by less effective preventive maintenance and technical inspections that were only visual. This condition caused 39 breakdown events with a total downtime of 41 hours. Repair recommendations are carried out through insert redesign, precision machining, hardening process, re-hard chrome, and improvement of inspection flow and tooling monitoring. In conclusion, improving the quality of inserts and strengthening the preventive maintenance system has been proven to be able to reduce the potential for repeated damage and increase the reliability of the stamping process.

References

[1] A. Bani Syaher, M. Mukti, I. Ramadhan, and A. Z. Alfaritsy, “Pendekatan Lean Manufacturing Menggunakan Metode Value Stream Mapping (VSM) Pada Umkm Samikem Sablon,” Jurnal Ilmiah Penelitian Mahasiswa, vol. 2, no. 4, pp. 423–432, 2024, doi: 10.61722/jipm.v2i4.303.

[2] K. Nadiyah, M. I. Senjawati, and G. R. Putri, “Perbaikan Sistem Kerja Proses Produksi Tahu pada PT XYZ menggunakan Peta-Peta Kerja,” JLSAT, vol. VI, no. 1, pp. 26–30, 2024.

[3] N. Fithri Azizah, R. Agil Apriani, F. P. Mahardika, M. A. Zikra Zizo, F. Aji Pradana, and A. Azzam, “Analisis Perancangan Tata Letak Menggunakan Metode Activity Relationship Chart (ARC) dan Computerized Relationship Layout Planning (CORELAP) Pada CV. Tunas Karya,” Jurnal Teknik Industri, vol. 9, no. 1, pp. 86–94, 2023.

[4] D. Mariboto et al., “Perancangan Ulang Tata Letak Untuk Pengoptimalisasian Ruang Pada Toko Ritel RDSP Bogor,” Jurnal Teknologi dan Manajemen Industri Terapan (JTMIT), vol. 2, no. 2, pp. 135–143, 2023.

[5] N. N. Suwandi and K. Suhada, “Penerapan Lean Manufacturing dengan Metode Value Stream Mapping untuk Mengurangi Cycle Time pada Bagian Perakitan Spring Mattress di PT X,” Journal of Integrated System, vol. 7, no. 2, pp. 111–133, Jan. 2025, doi: 10.28932/jis.v7i2.8694.

[6] A. F. Sasono, V. Yunior Ismail, H. R. Asworo, A. Budiman, and D. Dhivari, “Pengaplikasian OMH, FTC, ARC, ATBD, ARD, dan AADDalam Perencanaan Tata Letak Fasilitas Pada PT.XYZDengan Menggunakan Software WinQSB,” Journal of Industrial and Engineering System, vol. 5, no. 1, pp. 42–49, 2024.

[7] G. S. Rasikhak, K. Putri Kurnia, N. H. Istiqomah, C. A. Puteri, and N. Lestari, “Analisis Perancangan Ulang Tata Letak Fasilitas UD. Osha Snack Menggunakan Metode ARC dan TCR,” Indonesian Research Journal on Education, vol. 4, no. 4, pp. 2073–2079, 2024.

[8] E. Sulistyowati and M. Munawaroh, “Integrating Value Stream Mapping, Waste Assessment Model, and Root Cause Analysis to Improve Loading–Unloading Efficiency at PT XYZ,” Jurnal Teknik Industri Terintegrasi, vol. 8, no. 3, pp. 3599–3604, Jul. 2025, doi: 10.31004/jutin.v8i3.49182.

[9] S. Meutia, Fatimah, and N. Tumangger, “Analisis Gerakan Dan Pengukuran Waktu Kerja Untuk Mengurangi Pemborosan Gerakan Dengan Metode MOST (Maynard Operation Sequence Technique),” Jurnal Industri Samudra, vol. 4, no. 2, pp. 1–11, 2023.

[10] I. Bagus Suryaningrat and B. Herry Purnomo, “Penerapan value stream mapping untuk peningkatan produktivitas produksi okra beku di PT. MDT,” Jurnal Teknologi Industri Pertanian, vol. 16, no. 4, pp. 599–610, Dec. 2023, doi: 10.21107/agrointek.v16i4.12110.

[11] F. Fahlevi, E. Amrina, B. Ibramgara, and Y. Savitri, “Penerapan Lean Manufacturing menggunakan Metode VSM dan 5S pada UMKM di Kota Padang,” Jurnal Sains dan Teknologi: Jurnal Keilmuan dan Aplikasi Teknologi Industri, vol. 25, no. 1, pp. 28–43, Jun. 2025, doi: 10.36275/ny28qw84.

[12] S. A. Nuraini and S. Dewi, “Perancangan tata letak workshop menggunakan metode Systematic Layout Planning (SLP) di pergudangan Central Industrial Park,” Jurnal Teknik Industri Terintegrasi, vol. 8, no. 1, pp. 736–744, Jan. 2025, doi: 10.31004/jutin.v8i1.40280.

[13] P. Anggela, A. Y. M. Nababan, and I. Sujana, “Perancangan Ulang Tata Letak Fasilitas Dengan Metode Systematic Layout Planning Pada PT Tri Mandiri Sejati,” Jati Unik : Jurnal Ilmiah Teknik dan Manajemen Industri, vol. 7, no. 1, Oct. 2023, doi: 10.30737/jatiunik.v7i1.3582.

[14] Z. Khaerul Fajri, “Perancangan Sistem Kerja Pada Area Produksi Strainer 4W di PT Assyifa Teknik Mandiri,” Jurnal Pengabdian Masyarakat, vol. 4, no. 2, pp. 70–76, 2025, doi: 10.61193/jpme.v4i2.74.

[15] V. Nadia, E. Retnaningtyas, F. Valentino, and R. Wahyudi, “Usulan Perbaikan dan Standarisasi Sistem Kerja pada Proses Produksi Baja Ringan Jenis Reng di PT. Pratama Mandiri Paksi,” Jurnal Sustainability, Ergonomics, Optimization, and Application of Industrial Engineering, vol. 1, no. 2, pp. 76–85, 2024.

[16] F. Maulana Fajri, “Usulan Perbaikan Tata Letak Produksi Meja Lipat Menggunakan Metode Blocplan,” Jurnal Syntax Admiration, vol. 3, no. 3, pp. 529–545, Mar. 2022, doi: 10.46799/jsa.v3i3.403.

[17] A. Bani Syaher, M. Mukti, Ramadhan Irfan, and A. Z. Alfaritsy, “Pendekatan Lean Manufacturing Menggunakan Metode Value Stream Mapping (VSM) pada UMKM Samikem Sablon,” Jurnal Ilmiah Penelitian Mahasiswa, vol. 2, no. 4, pp. 423–432, 2024, doi: 10.61722/jipm.v2i4.303.

[18] V. Nadia, E. Retnaningtyas, F. Valentino, and R. Wahyudi, “Usulan Perbaikan dan Standarisasi Sistem Kerja pada Proses Produksi Baja Ringan Jenis Reng di PT. Pratama Mandiri Paksi,” Jurnal Sustainability, Ergonomics, Optimization, and Application of Industrial Engineering, vol. 1, no. 2, pp. 76–85, 2024.

Downloads

Published

04/01/2026

How to Cite

[1]
“Review of Problem Tooling Breakdown Fixes at the Op10 Part Panel Anniversary, RR W/House Inn, RR L/R (RH) at Pt. Summit Adyawinsa Indonesia”, jse, vol. 11, no. 1, Jan. 2026, Accessed: Apr. 28, 2026. [Online]. Available: https://jse.serambimekkah.id/index.php/jse/article/view/1468

Similar Articles

11-20 of 504

You may also start an advanced similarity search for this article.