Analisis Penjadwalan Proyek Menggunakan Metode Repetitive Scheduling Method (RSM)

Authors

  • Stevan Febrian Amiano Universitas Palangka Raya Author
  • Apria Brita Pandohop Gawei Universitas Palangka Raya Author
  • Dewantoro Universitas Palangka Raya Author
  • Veronika Happy Puspasari Universitas Palangka Raya Author
  • Almuntofa Purwantoro Universitas Palangka Raya Author

Keywords:

Repetitive Scheduling Method, Penjadwalan Proyek, Efisiensi waktu dan biaya, Proyek konstruksi repetitif, Produktivitas Pekerja

Abstract

Effective scheduling is a key factor in the success of construction projects. The Repetitive Scheduling Method (RSM) is a scheduling method designed for projects with repetitive activities, such as housing developments, high-rise buildings, highways, or bridges. This study aims to analyze the application of the RSM method in the Menteng VIII Housing Project in Palangka Raya. By comparing the project duration and cost before and after the implementation of RSM, this study found that the project duration could be reduced by 33.33%, from 231 days to 154 days, resulting in a total labor cost savings of IDR 15,700,000 per housing unit. These results demonstrate the effectiveness of RSM in improving time and cost efficiency in construction projects. The study also emphasizes that RSM reduces workers' idle time, increases productivity, and maintains work continuity. The application of RSM in this project is expected to serve as a reference for construction project managers in selecting a more optimal and efficient scheduling method. Thus, RSM can be one of the best alternatives in scheduling projects with repetitive work patterns.

References

[1] A. P. A. Putra dan G. Sarya, “Analisis Penjadwalan Dan Alokasi Biaya Menggunakan Metode Line of Balance Pada Proyek,” J. Keilmuan, vol. 5, hal. 390–398, 2022.

[2] I. Risangaji, “Evaluasi Kinerja Biaya Dan Waktu Pelaksanaan Proyek Dengan Metode Konsep Nilai Hasil (Evaluation of Work Performance and Schedule Performance of Project Implementation Using Earned Value Method),” J. Ekon. Vol. 18, Nomor 1 Maret201, vol. 2, no. 1, hal. 41–49, 2020, [Daring]. Tersedia pada: http://jurnal.untad.ac.id/jurnal/index.php/JTSI/article/viewFile/2410/1571

[3] Syaiful, Ahmad. "Analisis Penjadwalan Ulang dengan Menggunakan Metode PERT (Program Evaluation And Review Technique)(Rescheduling Analysis With Pert Methode)(Studi Kasus: Hotel Bhayangkara)." (2018).

[4] M. A. Aulia, A. H. Farisi, M. A. Wibowo, dan A. Hidayat, “Balance Pada Proyek Konstruksi Repetitif ( Studi Kasus : Proyek Pembangunan Apartemen,” J. Karya Tek. Sipil, vol. 6, no. 1, hal. 211–219, 2017.

[5] Project Management Institute, Chapter 3.10 Optimize Risk Responses, no. July. 2021.

[6] Menteri Pekerjaan Umum Dan Perumahan Rakyat Nomor 1 Tahun 2022, “Pedoman Penyusunan Perkiraan Biaya Pekerjaan Konstruksi Bidang Pekerjaan Umum Dan Perumahan Rakyat,” Kementrian PUPR, hal. 1–18, 2022.

[7] Halimi, Jamalan. "Analisis Penjadwalan Ulang Dengan Menggunakan Metode LSM (Linier Scheduling Method/Line Of Balance)(Rescheduling Analysis With LSM/LOB Method)." (2018).

[8] N. Brusselaers, A. Fredriksson, D. Gundlegård, dan R. Zernis, “Decision support for improved construction traffic management and planning,” Sustain. Cities Soc., vol. 104, no. October 2023, hal. 105305, 2024, doi: 10.1016/j.scs.2024.105305.

[9] A. Tomar dan V. K. Bansal, “Scheduling of repetitive construction projects using geographic information systems: an integration of critical path method and line of balance,” Asian J. Civ. Eng., vol. 20, no. 4, hal. 549–562, 2019, doi: 10.1007/s42107-019-00123-3.

[10] P. Okoye, O. Ezeokoli, P. Uchenna Okoye, J. Ugochukwu Ezeokonkwo, dan F. Okechukwu Ezeokoli, “Building Construction Workers’ Health and Safety Knowledge and Compliance on Site,” J. Saf. Eng., vol. 2016, no. 1, hal. 17–26, 2016, doi: 10.5923/j.safety.20160501.03.

[11] D. Heigermoser, B. García de Soto, E. L. S. Abbott, dan D. K. H. Chua, “BIM-based Last Planner System tool for improving construction project management,” Autom. Constr., vol. 104, no. March, hal. 246–254, 2019, doi: 10.1016/j.autcon.2019.03.019.

[12] A. Bhaskara, A. A. Ginting, dan A. M. Masagala, “Penerapan Konstruksi Ramping terhadap Waste pada Ruang Lingkup Manajemen Proyek (Studi Kasus: Proyek Pembangunan Gedung Auditorium di Yogyakarta),” Semesta Tek., vol. 25, no. 1, hal. 80–88, 2022, doi: 10.18196/st.v25i1.13403.

[13] S. H. Kim, “Free-electron two-quantum stark radiation driven by the electric wiggler associated with density modulation in a hydrodynamic free-electron laser,” J. Korean Phys. Soc., vol. 60, no. 5, hal. 674–679, 2012, doi: 10.3938/jkps.60.674.

[14] A. A. Wiranata, A. . D. P. Dewi, dan I. M. Nuryawan, “Penggunaan Metode Penjadwalan Berulang (Repetitive Scheduling Method) pada Pengerjaan Proyek Perumahan (Studi Kasus pada Proyek Perumahan Beranda Mumbul),” J. Ilm. Tek. Sipil, vol. 13, no. 2, hal. 174–182, 2009.

[15] R. B. Harris dan P. G. Ioannou, “Repetitive Scheduling Method,” Cent. Constr. Eng. Manag., no. 98–35, hal. 56, 1998.

Downloads

Published

22/03/2025

Issue

Section

Articles

How to Cite

[1]
“Analisis Penjadwalan Proyek Menggunakan Metode Repetitive Scheduling Method (RSM)”, jse, vol. 10, no. 2, Mar. 2025, Accessed: Mar. 25, 2025. [Online]. Available: https://jse.serambimekkah.id/index.php/jse/article/view/812

Similar Articles

1-10 of 451

You may also start an advanced similarity search for this article.