Optimalisasi Penjadwalan Proyek Pembuatan Reactor Tank Dengan Menggunakan Critical Path Method

Authors

  • Muhammad Wibbie Wiweka Subono Program Studi Teknik Industri, Universitas Pembangunan Nasional Veteran Jawa Timur Author
  • Sumiati Program Studi Teknik Industri, Universitas Pembangunan Nasional Veteran Jawa Timur Author

Keywords:

Manajemen Proyek, Konstruksi, Penjadwalan, Crictical Path Method (CPM), Optimalisasi, POM-QM

Abstract

Project management itself is the process of combining tools, resources and techniques to achieve predetermined goals. If all activities are managed according to clear objectives and outcomes, the project will run according to plan. On-site project monitoring should be carried out regularly to predict possible errors in terms of time, cost, etc. The purpose of this study was to analyse the schedule, identify the critical path and compare the total labour costs in the manufacture of reactor tanks by PT. PDK. The approach used is the Critical Path Method (CPM) supported by POM-QM software. The study is descriptive with a quantitative approach. The conclusions are as follows: First, the activity schedule consists of 28 activities, with the activity sequence A-B-C-D-E-F-G-H-I-J-K-L-M-N-O-P-Q-R-S-T-U-V-W-X-Y-Z-AA-AB with a duration of 158 days; Second, the results of the CPM analysis show a pattern of activity paths, where the critical path of the reactor tank construction project is A-B-C-D-E-F-G-H-I-J-K-L-M-Z-AA-AB with a duration of 108 days; and thirdly, the application of the CPM method successfully reduced the labour cost of the project from Rp 97,960,000 to Rp 66,960,000, which means that there was a cost saving of Rp 31,000,000. The application of project management through CPM analysis shows that the project schedule and cost become more optimal, effective and efficient, and the results of this study are consistent with previous studies that discuss project management methods.

References

[1] Noviyarsi, Noviyarsi, et al. "Analisis Pengaruh Faktor-Faktor Produktivitas Kerja Proyek Konstruksi Dengan Relative Importance Index (RII) Dan Regresi Linear Berganda." Jisi: Jurnal Integrasi Sistem Industri 10.1 (2023): 27-38.

[2] Lamato, Fadlan, Arfan Utiarahman, and Mohammad Yusuf Tuloli. "Analisis earned value terhadap proyek pembangunan renovasi gedung kantor BPJN." Jurnal Vokasi Sains Dan Teknologi 1.2 (2022): 46-53.

[3] I. H. Khotimah, N. N. Rodhi, and A. Tjandra, “Analisis Pengendalian Waktu Proyek Menggunakan Metode Critical Path Method ( CPM ) ( Studi Kasus : Proyek Rehabilitasi Jalan Dander - Bubulan ) De ’ Teksi : Jurnal Teknik Sipil,” vol. 9, no. 2, pp. 60–69, 2024.

[4] F. Sinurat and F. Misdalena, “Analisis Manajemen Proyek Dengan Metode Critical Path Method (CPM) Pada Proyek Pembangunan Gedung Chandra Tanjung Karang,” pp. 2–11, 2024, doi: 10.33364/konstruksi/v.22-2.2131.

[5] T. S. Soeparyanto, R. Nuhun, A. Annisa, Y. Yusran, H. Ariatno, and L. O. M. Zulfitrah, “Analysis Of Project Scheduling Using The CPM Method (Case Study Of Prayer Room Construction In PT. X Empalecement Complex),” J. Civ. Eng. Plan., vol. 5, no. 1, pp. 16–24, 2024, doi: 10.37253/jcep.v5i1.9206.

[6] W. H. M Nadhif Auliya Authon, “Evaluasi Proyek Perbaikan Ducting Inlet SLC Boiler PT. Semen Indonesia (Persero) TBK Dengan Critical Path Method (CPM) dan S-Curve,” J. Manag. Bussines, vol. 13, no. 1, pp. 104–116, 2023.

[7] N. N. Rodhi, “Perencanaan Manajemen Proyek Dalam Meningkatkan Efektifitas Kinerja Sumber Daya Manusia Di Bojonegoro,” DEARSIP J. Archit. Civ., vol. 4, no. 01, pp. 25–32, 2024, doi: 10.52166/dearsip.v4i01.6262.

[8] F. I. Wiranda and H. Murnawan, “Manajemen Proyek Pengerjaan Pipa Air pada PT. X Menggunakan Metode CPM dan PERT,” J. Tek. Ind. Terintegrasi, vol. 7, no. 2, pp. 1139–1146, 2024, doi: 10.31004/jutin.v7i2.28508.

[9] M. F. Chasan, D. A. S. Fauji, and H. Purnomo, “Evaluasi Penjadwalan Waktu Dan Biaya Dengan Metode CPM Dan Gantt Chart Pada Proyek Pembangunan Rumah Tipe 60/72 Griya Keraton Sambirejo Kediri,” Simp. Manaj. dan Bisnis, no. 1, pp. 100–108, 2022, [Online]. Available: https://proceeding.unpkediri.ac.id/index.php/simanis/article/view/1678

[10] N. M. Astari et al., “Perencanaan Manajemen Proyek Dengan Metode CPM (Critical Path Method) dan PERT (Program Evaluation And Review Technique) Pertumbuhan infrastruktur daerah diberbagai sektor terjadi dengan cepat dan terjadi pertumbuhan pada fasilitas infrastruktur Dibut,” vol. 13, pp. 164–180, 2021.

[11] Fadila, Nur. Penerapan Manajemen Proyek Dengan Metode CPM (Critical Path Method) Pada Pembangunan Rumah Subsidi Di Perumahan Sultan Area City Kota Pinang. Diss. Fakultas Teknik, Universitas Islam Sumatera Utara, 2024.

[12] N. Saputra, E. Handayani, and A. Dwiretnani, “Analisa Penjadwalan Proyek dengan Metode Critical Path Method (CPM) Studi Kasus Pembangunan Gedung Rawat Inap RSUD Abdul Manap Kota Jambi,” J. Talent. Sipil, vol. 4, no. 1, p. 44, 2021, doi: 10.33087/talentasipil.v4i1.48.

[13] Saputra, Ichwan Hadi, Yeni Erina, and Nova Nevila Rodhi. "Analisis Pengendalian Waktu dan Biaya Proyek Konstruksi Dengan Metode CPM (Critical Path Method)." Innovative: Journal Of Social Science Research 4.6 (2024): 7797-7807.

[14] I. Habibi, F. Z. Nugraha, and S. Sutrisno, “Penerapan Critical Path Method pada Penyelesaian Proyek Rehabilitasi Jalan Parigi Lama di Kabupaten Sumedang,” Go-Integratif J. Tek. Sist. dan Ind., vol. 4, no. 01, pp. 1–10, 2023, doi: 10.35261/gijtsi.v4i01.8307.

[15] M. Muhamad, L. A. Darmawan, and W. Wahyudin, “Analisa Optimalisasi Waktu Kerja Mekanik pada Dealer Motor XYZ dengan Metode Hungarian Menggunakan Aplikasi POM-QM,” JURMATIS (Jurnal Manaj. Teknol. dan Tek. Ind., vol. 4, no. 1, p. 37, 2022, doi: 10.30737/jurmatis.v4i1.1982.

Downloads

Published

12/01/2025

How to Cite

[1]
“Optimalisasi Penjadwalan Proyek Pembuatan Reactor Tank Dengan Menggunakan Critical Path Method”, jse, vol. 10, no. 1, Jan. 2025, Accessed: Jan. 12, 2025. [Online]. Available: https://jse.serambimekkah.id/index.php/jse/article/view/714

Similar Articles

1-10 of 251

You may also start an advanced similarity search for this article.