Analisis Penjadwalan Percepatan Proyek Outfitting Machinery Blok ASA 2A S Pada Pembuatan Kapal A Menggunakan Microsoft Project dengan Precedence Diagram Method di PT. XYZ
Keywords:
Penjadwalan proyek, Percepatan Proyek, Precedence Diagram Method, Microsoft Project, Efisiensi waktuAbstract
The shipbuilding project is highly complex, involving multiple phases and interdependent activities with extended durations. One of the main challenges in this project is how to design an effective schedule to minimise the completion time without compromising the quality of work. The objective of this study is to analyse the project acceleration of the Machinery Outfitting of Block ASA 2A S of the A Ship at PT. XYZ using Microsoft Project software and the Precedence Diagram Method (PDM). The research process began with the collection of data on job sequences, activity durations and dependencies between activities. This data was processed using PDM to identify the critical path, which consisted of eight main activities: A, B, D, E, G, H, K and M. Through critical path analysis, rescheduling was carried out to accelerate project completion. The results show that the project duration was successfully reduced from the original plan of 61 days to 54 days, enabling PT. XYZ to complete the machinery outfitting of Block ASA 2A S on the A Ship project by 1 September 2020. This improvement increased time and cost efficiency without compromising project quality. This study demonstrates the effectiveness of using Microsoft Project with PDM to manage complex project schedules.
References
[1] D. J. Yuna Sutria, “Peranan Bagian Operasional Dalam Mengurus Izin Olah Gerak Kapal Di Kantor Kesyahbandaran Utama Belawan Pada Pt.Naval Global Trans Cabang Belawan,” Journal of Maritime and Education, 2022.
[2] F. F. I. P. K. H. a. M. M. A. Saputra, “Penerapan Lean Manufacturing di CV. Wahana Karya,” 2023.
[3] W. A. A. F. Z. Oryza Rafi Oceandy, “Analisis Efektifitas Material HandlingRe-LayoutGalangan KapalPT. Yasa Wahana Tirta Samudera dengan Metode Systematic Layout Planning,” Jurnal Teknik Perkapalan, 2023.
[4] M. B. Aqsal Ardiana Timur Raja, “Pengembangan Sistem Aplikasi Manajemen Reparasi Kapal Berbasis Web Dengan,” Jurnal Sumberdaya Bumi Berkelanjutan, 2022.
[5] C. S. Myra Beatrice Soeltanong, “Perencanaan Produksi dan Pengendalian Persediaan pada Perusahaan Manufaktur,” JRAP (Jurnal Riset Akuntansi dan Perpajakan), 2021.
[6] E. C. B. P. O. Y. &. R. N. K. Sinta Aryani, “Pendampingan Pengendalian Persediaan dan Penjadwalan Produksi Usaha Kripik Tempe Pesantren Arafah, Cililin, Kab. Bandung Barat,” Jurnal Pengabdian kepada Masyarakat Nusantara (JPkMN), 2024.
[7] D. Sanjaya, “Penjadwalan Produksi Anyaman Bambu Dengan Menggunakan Metode Shortest Processing Time (SPT) pada IKM Anyaman Bambu Gunung Tajem Di Salem Brebes Jawa Tengah,” Jurnal Mahasiswa Industri Galuh, 2020.
[8] Sudiantini, Dian, et al. "Pengaruh Pengendalian Persediaan Bahan Baku Terhadap Proses Produksi." Musytari: Neraca Manajemen, Akuntansi, dan Ekonomi 2.8 (2023): 133-143.
[9] H. Rudiawan, “Peranan Manajemen Produksi dalam Menyelaraskan Kinerja Perusahaan,” Jurnal Manajemen FE-UB, 2021.
[10] d. U. N. A. P. Salsabila Sembiring, “Penjadwalan Mesin dengan Menggunakan Metode Algoritma Genetika dan metode Campbell Dudek Smith (CDS),” TALENTA Conference Series: Energy & Engineering, 2023.
[11] F. H. R. I. Mohammad Adjie Irfansah, “Optimasi Penjadwalan Produksi Menggunakan Metode Campbell Dudek Smith (CDS) Dan Metode,” Proceedings Conference On Design Manufacture Engineering And Its Application, 2023.
[12] E. A. Nugraha Kusuma Ningrat, “Penerapan Metode Distribution Requirementplanning (DRP) Dalam Penjadwalan Distribusi Produk di UKM SB Jaya Ciamis,” Jurnal Industrial Galuh, 2023.
[13] M. A. A. P. Sadat N S. Sidabutar, “Penjadwalan Operasi Mesin Produksi Dengan Metode CDS (Campbell Dudek Smith) di PT Tjokro Bersaudara Balikpapanindo,” Proton, 2020.
[14] E. S. S. Ali Murdani Lubis, “Optimasi Penjadwalan Proyek Pembangunan Jalan Tol Becakayu Seksi 1BC Dengan Menggunakan Metode CPM dan PERT,” Jurnal SEOI -Fakultas Teknik Universitas Sahid Jakarta, 2021.
[15] W. S. Syahrul Fadlil Syabani, “Optimasi Penjadwalan Produksi Menggunakan Metode Nawaz Enscore Ham,” Jumantara, 2022.
[16] I. S. F. Tolu Tamalika, “Analisis Penjadwalan Waktu Pekerjaan Proyek Poltekkes Jurusan Farmasi Tahap I dalam Perspektif Manajemen Proyek,” Jurnal Pendidikan Tambusai, 2022.
[17] F. N. M. Vendie Abma, “Cash Flow Proyek Dengan Sumber Modal Bank Syariah Pada Pembangunan Dan Rehabilitasi Gedung Pelayanan Kesehatan Pemerintah Kabupaten Gunung Kidul,” Construction and Material Journal, 2020.
[18] Pratama, Randy Anzas, Basuki Arianto, and Ervini Meladiyani. "Penjadwalan Produksi Agregat Dengan Metode Model Transportasi Guna Mengoptimalkan Produksi." Jurnal Teknik Industri 10.1 (2021).
[19] Riesna, Deby Mega Rizkia, et al. "Identifikasi Platform dan Faktor Sukses dalam Manajemen Proyek Teknologi Informasi." Jurnal teknologi riset terapan 1.1 (2023): 1-9.
[20] S. B. A. Indah Puspitorini, “Microsoft Project telah banyak dikenalsebagai sebuah aplikasi pengelola proyek yang cukup handal dan dapat bekerja dengan baik,” Jurnal Minfo Polgan, 2023.
[21] M. N. Sholeh, Modul Pelatihan Microsoft Project, Universitas Diponegoro, 2020.
[22] Gazalba, Zaedar, and I. Gede Putu Warka. "Evaluasi Kewajaran Schedule Kontraktor Menggunakan Work Breakdown Structure (WBS) dan Microsoft Project (Studi Pada Proyek Pembangunan SDN 5 Sokong, Tanjung, Lombok Utara)." Ganec Swara 16.1 (2022): 1285-1296.
[23] P. E. Y. K. Sri Rahayu, “Penerapan Metode CPM Dan CCPM untuk Perencanaan Sumber Daya Dan waktu Penyelesaian Multi Proyek,” JISO: Journal Of Industrial And Systems Optimization, 2022.
[24] Prafitasiwi, Avisha Gita, et al. "Pelatihan Manajemen Waktu Proyek Konstruksi Berbasis Aplikasi Microsoft Project Pada Siswa SMA/SMK." DedikasiMU: Journal of Community Service 5.2 (2023): 199-206.
[25] I. M. A. P. Y. R. W. Made Widya Jayantari, “Analisis Biaya Serta Percepatan Durasi Proyek Menggunakan Metode Crashing Dengan Sistem Waktu Gilir Kerja Dan Lembur(Studi Kasus: Puskesmas Wolowaru, Kabupaten Ende),” Reinforcement Review in Civil Engineering Studies and Management, 2022.
[26] B. F. M. G. Y. &. P. P. A. Tombokan, “Analisis Hubungan Pekerjaan Dan Lintasan Kritis Pada Penjadwalan Proyek Pembangunan Rumah Sakit Umum Daerah Dr. Sam Ratulangi Tondano,” Tekno, 2022.
[27] R. M. &. B. C. A. F. Pratiwi, “Optimalisasi Waktu Dan Biaya Menggunakan Time Cost Trade Off Method (TCTO) Dan Precedence Diagram Method (PDM) Pada Pembangunan Drainase Jalan Tol Km. 35 Balikpapan-Samarinda.,” Jurnal TRANSUKMA, 2020.
[28] L. O. a. I. B. Oktafiana, “Comparative Analysis of CPM, PDM and PERT Methods in Ship Repair Scheduling Planning KN. RB 309 Ternate 01,” Berkala Sainstek, 2022.
[29] T. T. A. G. Y. M. Sthefanus A. Lengkong, “Analisis Penjadwalan Proyek Menggunakan Metode PDM Dengan Menggunakan Konsep Cadangan Waktu Pada Proyek Pembangunan Balai Kesehatan Ibu Dan Anak Kota Manado,” TEKNO, 2023.
[30] I. P. M. D. C. Sheila Ayu Kirana Prabani, “Analisa Crashing Project Menggunakan Metode Time Cost Trade Off Pada Pembangunan Mooring Boat Milik PT. Pertamina Trans Kontinental Akibat Modifikasi Desain Bottom Keel,” Jurnal Teknik Perkapalan, 2021.
Downloads
Published
Issue
Section
License
Copyright (c) 2024 Galang Aryaduta, Farida Pulansari (Author)
![Creative Commons License](http://i.creativecommons.org/l/by/4.0/88x31.png)
This work is licensed under a Creative Commons Attribution 4.0 International License.