Optimalisasi Sumber Daya Tenaga Kerja Proyek Pembangunan Hotel Amaris Manado Dengan Metode Resource Leveling

Authors

  • Stefani Switly Peginusa Politeknik Negeri Manado Author
  • Cyntha Tendean Politeknik Negeri Manado Author
  • Arnetha S. Raintung Universitas Pembangunan Indonesia Author

Keywords:

resource leveling, microsoft project, optimization, duration, manado, amaris hotel

Abstract

Construction projects inevitably encounter challenges related to time, labor, cost, and materials. If these issues aren't addressed promptly and effectively, new problems inevitably arise, such as delays in work duration, inefficient labor distribution, and delays in equipment and materials. The construction of the Amaris Hotel in Manado encountered significant challenges, particularly in structural work. A clear imbalance in labor allocation was identified, where the availability of labor in the field did not align with the project's needs. This discrepancy was exposed through unit price analysis of daily reports. This study aims to optimize human resources using the Resource Leveling method with Microsoft Project 2021 Software, addressing the ground floor structure to the roof floor. The results of the analysis showed that the duration of time required after the analysis did not change, namely 303 days. The study also determined the number of effective workers: 63 laborers, 34 builders, 3 foremen, and 3 building foremen.

References

[1] P. S. Derianto and Y. P. Kristiutami, “Standar Operasional Prosedur Room Service Amaroossa Hotel Bandung,” J. Pariwisata, vol. 2, no. 1, pp. 15–21, 2015, [Online]. Available: https://ejournal.bsi.ac.id/ejurnal/index.php/jp/article/view/295

[2] P. Benedikta, “Kajian Terhadap Limbah Konstruksi Pada Proyek Pembangunan Hotel @Hom Di Yogyakarta,” vol. 6, no. 2, pp. 2–4, 2020, [Online]. Available: http://www.sangkareang.org/

[3] Badan Pusat Statistik Provinsi Sulawesi Utara, Statistik Pariwisata Provinsi Sulawesi Utara Tahun 2023, vol. 2. Manado, 2024.

[4] R. Agusbushro, V. H. Makarau, and A. Sembel, “Analisis Kebutuhan Prasarana Dan Sarana Pariwisata Di Kawasan Taman Nasional Bunaken Kecamatan Bunaken Kepulauan Kota Manado,” Spasial, pp. 122–131, 2015, [Online]. Available: https://ejournal.unsrat.ac.id/index.php/spasial/article/view/9094

[5] S. Kiswati and U. Chasanah, “Perencanaan Manajemen Proyek Dalam Meningkatkan Efektifitas Kinerja Sumber Daya Manusia Di Semarang Jawa Tengah,” Neo Tek., vol. 6, no. 1, 2020.

[6] A. . D. P. Dewi, I. G. K. Sudipta, and D. S. Setyowati, “Analisis Aspek Sumber Daya Manusia Terhadap Kinerja pada Proyek Konstruksi Di Kabupaten Bandung,” J. Ilm. Tek. Sipil, vol. 20, no. 2, 2016.

[7] A. Radithya Yahya and V. Abma, “Analisis Kebutuhan Tenaga Kerja Dengan Menggunakan Metode Resource Levelling,” Civ. Eng. Res. Forum, vol. 2, no. January, pp. 163–175, 2022.

[8] Septiana Rachmawati, “Implementasi Konsep Bim 4D Dalam Perencanaan Time Schedule Dengan Analsis Resources Levelling (Implementation of 4D Bim Concept in Time Schedule Planning With Resources Levelling Analysis),” 2022.

[9] I. Puspitorini and S. Bayu Adhi, “Penerapan Resource Allocation dan Levelling tenaga Kerja Pada Proyek Konveksi,” J. Minfo Polgan, vol. 12, no. 2, pp. 2728–2735, 2024, doi: 10.33395/jmp.v12i2.13359.

[10] S. Sholeha and Z. R. Kamandang, “Analisis Biaya pada Implementasi Resource Leveling Tenaga Kerja,” J. Komposit J. Ilmu-ilmu Tek. Sipil, vol. 8, no. 1, pp. 57–65, 2024, [Online]. Available: https://doi.org/10.32832/komposit.v8i1.14519

[11] Riswan, R. Maulana, A. Hermawan, and S. N. Sari, “Analisis Optimalisasi Jumlah Tenaga Kerja Terhadap Time Schedule Pada Proyek Rehabilitasi Smp Negeri 2 Wates,” STORAGE J. Ilm. Tek. dan Ilmu Komput., vol. 3, no. 1, pp. 35–44, 2024, doi: 10.55123/storage.v3i1.3137.

[12] A. R. Yahya, “Analisis Kebutuhan Tenaga Kerja Dengan Metode Resource Levelling (Analysis Of Labor Requirements Using The Resource Levelling Method) (Studi Kasus: Proyek Pembangunan Gereja Katolik Santa Maria Penolong Abadi, Samarinda, Kalimantan Timur),” 2022, [Online]. Available: htthttps://dspace.uii.ac.id/handle/123456789/38546?show=full

[13] W. Febriana and U. A. Aziz, “Analisis Penjadwalan Proyek Dengan MetodePERTMenggunakan Microsoft Project 2016,” J. Sains dan Seni ITS, vol. 5, no. 1, 2021.

[14] P. Lynna and Syafriandi, Manajemen Konstruksi dengan Aplikasi Microsoft Project. 2019.

[15] P. G. Gunaga and G. George, “Planning, Scheduling and Cost Estimation Of Villa Project Using Microsoft Project,” Int. J. Res. Appl. Sci. Eng. Technol., vol. 10, no. 9, pp. 1779–1792, 2022, doi: 10.22214/ijraset.2022.46885.

Downloads

Published

29/03/2025

Issue

Section

Articles

How to Cite

[1]
“Optimalisasi Sumber Daya Tenaga Kerja Proyek Pembangunan Hotel Amaris Manado Dengan Metode Resource Leveling”, jse, vol. 10, no. 2, Mar. 2025, Accessed: Apr. 01, 2025. [Online]. Available: https://jse.serambimekkah.id/index.php/jse/article/view/843

Similar Articles

1-10 of 61

You may also start an advanced similarity search for this article.