Project Scheduling of Aruna Solar Power Plant Access Road and Pond Construction Using CPM and PERT
Keywords:
penjadwalan proyek, CPM, PERT, jalur kritis, proyek konstruksiAbstract
The success of construction projects is highly influenced by scheduling effectiveness, as project delays may lead to cost overruns, reduced productivity, and failure to achieve project targets. The Access Road and Pond Construction Project for the Aruna Solar Power Plant, undertaken by PT Wan Artha Nata Indonesia, experienced delays compared to the planned schedule. This study aimed to analyze project scheduling using the Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT), identify critical activities, determine project completion duration, and evaluate schedule uncertainty. A descriptive quantitative approach with a case study design was employed. Data were collected through field observations, interviews, and project documentation, including the Work Breakdown Structure (WBS), project schedules, activity durations, and precedence relationships. CPM analysis was used to identify the critical path and determine the project duration, while PERT analysis was applied to evaluate schedule uncertainty using optimistic, most likely, and pessimistic time estimates. The results indicated that the minimum project duration was 203 days, with several activities identified as critical activities having no scheduling flexibility. Furthermore, the PERT analysis revealed the existence of schedule uncertainty caused by weather conditions, site constraints, material delivery delays, and permit approval processes.
References
[1] P. Adhi Pradipta Dhana, I. Gusti Lanang Made Parwita, and I. Wayan Darya Suparta, “Analisis Penjadwalan Proyek Menggunakan Metode Critical Path Method (CPM) Dan Program Evaluation And Review Technique (PERT) (Studi Kasus: Proyek Pembangunan SMPN 3 Kuta, Badung, Bali),” in Prosiding Seminar Nasional Ketekniksipilan Bidang Vokasional XIII, 2025, pp. 862–873.
[2] K. Bima Purnomo and M. Ardan, “Evaluasi Penerapan Teknik Crashing dalam Manajemen Waktu Pembangunan Rumah Subsidi dengan Metode CPM dan PERT (Studi Kasus Rumah Pondok Alam Desa Sigara-Gara),” Jurnal Inersia, vol. 17, no. 1, pp. 32–43, 2022, doi: 10.33369/ijts.17.1.32-43.
[3] R. Avinika Ningtyas et al., “Tinjauan Penerapan Critical Path Method (CPM) dan Program Evaluation and Review Technique (PERT) Dalam Pembangunan Proyek Gedung X,” Construction and Material Journal, vol. 7, no. 1, pp. 65–71, 2025, [Online]. Available: http://jurnal.pnj.ac.id/index.php/cmj
[4] T. Sulistyani, T. R. Khusniyah, and A. D. Susilawati, “Licensed under a Creative Commons Attribution-NonCommercial 4.0 International License Manajemen Proyek Critical Path Method dan Program Evaluation and Review Technique,” Jurnal Manajemen dan Bisnis, vol. 5, no. 2, pp. 193–204, 2025, doi: 10.24905/konsentrasi.v5i2.61.
[5] Ilham, Habir, and Tukimun, “An Integrated Critical Path Method and PERT Approach for Schedule Performance Evaluation of Drainage Construction Projects Article History,” International Journal of Industrial Engineering, vol. 3, no. 2, pp. 83–93, 2025, doi: 10.62157/ijietom.v3i2.114.
[6] F. Zaidan Nugraha, “Implementasi Penentuan Jadwal Dan Biaya Efektif Melalui Integrasi Metode CPM (Critical Path Metode) Dan PERT (Program Evaluation And Review Technique),” COSTING: Journal of Economic, Business and Accounting, vol. 7, no. 5, pp. 4616–4626, 2024.
[7] M. A. Rahman and B. Wicaksana, “Analisa Manajeman Waktu Menggunakan Metode CPM(Critical Path Method) dan PERT(Program Evaluation And Review Technique) Pada Proyek Pembangunan Ruang Kelas Baru Institut Agama Islam Nazhatut Thullab Pulau Madura,” Jurnal Review Pendidikan dan Pengajaran, vol. 7, no. 3, pp. 9206–9213, 2024.
[8] I. Cristo Marampa, P. Dana Pariawan Salain, and F. Moi, “Analisis Kerusakan Jalan dengan Metode Pavement Condition Index (PCI) dan Strategi Penanganannya pada Ruas Jalan Puri Gading Kelurahan Jimbaran Mahasiswa Sarjana Terapan Manajemen Proyek Konstruksi Jurusan Teknik Sipil,” in Prosiding Seminar Nasional Ketekniksipilan Bidang Vokasional XIII`, 2025, pp. 1140–1151.
[9] P. Ni Putu Dea Widyanti, I. Nyoman Sedana Triadi, and I. Gusti Lanang Parwita, “Perencanaan Metode Pelaksanaan Tangki Air Limbah Pada Resort Bambu Indah di Kawasan Ubud Gianyar dengan Metode CPM,” Ketekniksipilan Bidang Vokasional, vol. 4, no. 1, pp. 1–9, 2025.
[10] M. A. Perdana and R. P. Sari, “Optimalisasi Waktu Pelaksanaan Proyek Konstruksi Rumah Tinggal Menggunakan Metode CPM (Critical Path Method) dan PERT (Program Evaluation and Review Technique),” Jurnal Media Teknik dan Sistem Industri, vol. 6, no. 2, pp. 116–123, Sep. 2022, doi: 10.35194/jmtsi.v6i2.1944.
[11] T. Maharani and A. Herzanita, “Analisis Percepatan Waktu Proyek dengan Metode Crashing dan Last Planner System (LPS): Studi Kasus Proyek Pembangunan Gedung Fasilitas Pengembangan Produk Skala Pilot (Gedung No.34),” Construction and Material Journal, vol. 7, no. 2, pp. 295–309, 2025, [Online]. Available: http://jurnal.pnj.ac.id/index.php/cmj
[12] F. A. Achmad, Y. Prima, and A. Rumbyarso, “Multiscience Analisis Penjadwalan Proyek Klinik Spesialis Mata & Tht Ayani Dengan PERT & CPM,” Multiscience, vol. 1, no. 1, pp. 1–8, 2024.
[13] M. Farhan Fauzi, Y. Prima, A. Rumbyarso, and B. M. Siagian, “Analisa Penjadwalan Proyek Menggunakan CPM dan PERT Pada Proyek Pembangunan Gedung KONI Jakarta Pusat,” Jurnal Teknik dan Teknologi Indonesia, vol. 2, no. 3, pp. 1–11, 2024.
[14] S. Aulia and H. Cipta, “Network Planning Analysis Using CPM and PERT Methods on Optimization of Time and Cost,” Sinkron, vol. 8, no. 1, pp. 171–177, Jan. 2023, doi: 10.33395/sinkron.v8i1.11961.
[15] B. Desticioğlu Taşdemir, “Project Planning with CPM and PERT Methods: Example of Defence Industry,” Journal of Naval Sciences and Engineering, vol. 18, no. 2, pp. 363–385, 2022.
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Aurellia Dianty, Lifia Citra Ramadhanti (Author)

This work is licensed under a Creative Commons Attribution 4.0 International License.